Re-surfacing of Farrington Road Has Begun

0
775
(BIS Photos/Kristaan Ingraham)

Road resurfacing began on Farrington Road 9:30 a.m. to 2:00 p.m. as of March 5 — Monday through Friday for 10 working days.  The resurfacing of Farrington Road will extend from the “six-legged” roundabout to Boyd Road. There will be east and westbound lane closures implemented at various times for the duration of the works.

All eastbound traffic will be detoured to University Drive during the lane closures for milling and paving. During westbound lane milling and paving works, all westbound traffic will be detoured to West Bay Street. Additionally, as a result of westbound lane closures, all south-west bound traffic will be detoured to University Drive at Ajax Street. All connecting side roads along the length of Farrington Road will be closed. Provisions for access.